Having a plan you follow through is not all there is to project management. Namely, you ought to take the human factor into account. Let’s face it: people are not robots that can work 24/7/365. They will take days off, work in less than full capacity and make mistakes.
Importing your resources to BigPicture
Done. No, really. BigPicture uses the standard Assignee field in JIRA. As long as your tasks have it filled and are inside of the plugin’s Programs, you’re good to go. The Gantt will show the assignee of each task in the Icons column:
Customization
If Reporter is also filled, the Icons column will show two avatars, illustrated above. But let’s make our life a bit simpler. First, let’s remove the Assignee from Icons:
And add a separate Assignee column, along with full name display:
Much better. The reason for this was, however, not just clarity and sleeker looks. As long as a column is added, one can group and sort by the values of it.
This gives us a nice, visual overview of tasks divided by the assigned resource, with the number of tasks clearly stated next to his or her name.
Now, some of you might wonder why we’re not using Quick Filters for this purpose. You could create QFs of assignee=… format, one per each Resource. This would be a good way to show only selected resources at a time. However, this way requires JQL knowledge and may be unfeasible (imagine a corporation with 10,000 resources and creating all those filters).
Protip: While you cannot assign tasks to people on the Gantt chart, by selecting a task and hitting E you can do so:
Jan 2021
Deciding between BigPicture and BigPicture Enterprise? Check 6 signs your organization should upgrade to BigPicture Enterprise.
Jan 2021
Product and market diversification gives way to a new kind of diversity – such with various products, PM methodologies, and people coexisting and interacting in an organization. Here is an executive buyer’s guide to selecting the best PPM software for a diverse company (PM methodology-wise) – more
Jan 2021
What are the top 8 reasons to upgrade to BigPicture 8? If you are on Jira Cloud your BigPicture version was updated automatically. If you are on Server or Data Center it is your responsibility to update.
Progress tracking
I already went ahead and added some progress on these tasks. BigPicture can use JIRA Time Tracking, which is the very same mechanism as on your JIRA tasks, under the Log Work option:
Just make sure to select Time Tracking in the global configuration, as the custom field is there by default:
Now any and all work logged by your resources will appear on the Gantt chart. Well, in fact, not only there.
See also: Time tracking in BigPicture and BigGantt
Dedicated screen
The Resources module is pretty much the Gantt with grouping by Assignee turned on all the time and with no columns. You still have the timeline layout, and the familiar bar representation of tasks that you can drag and drop. The only big difference are the small numbers for each day of every resource.
These represent allocation of this resource and operate based on 3 values:
- Duration – how long a task is scheduled to take. This is the same duration as on the Gantt chart.
- Effort: the number of work hours that need to be spent on the task within the duration. This is the Original Estimate field, part of JIRA’s Time Tracking mentioned above.
- Capacity
Effort is simply distributed across duration. So, for example, a task with 3 days of duration and 9 hours of effort will be 3 days of 3 hours work each. Shortening a task will make it take less days, but increase the workload per day. Enlarging a task will result in the opposite.
Capacity is configured in the Administration section – it overlays the non-working days of a resource defined in Holiday Plans on your schedule, and also compares the maximum allocation defined in Workload Plans with the current one for color-coding. Red is over allocation, green is under allocation, and yellow is a more or less exact match.
Protip: the weekly scale of Resources has a special summary when the Capacity row is expanded.
The summary row is great for showing overall status of all your resources, selected ones if you also have Quick Filters set up for them. However, it really shines when you select a team via the dropdown in the upper-left corner:
Two kinds of Teams
To select them anywhere, you first ought to have some set up. There are two kinds of teams in BigPicture:
- Global teams, defined in the Administration section
- Program-specific teams, available under the Teams entry in the plugin’s header
The difference is very simple. Global teams can be assigned to any number of your Programs. Once created in Administration, you head to the Teams tab and just assign the desired Global teams. Here you can also create Program-specific teams, which will not be re-usable in other Programs. This approach is good only for ad-hoc teams or groups of resources.
Teams do two things. They allow you to filter the Resources view, and are also visible on the BigPicture’s Program Board as well as on the Scaled Agile Framework®-compliant Roadmap.
Program Board for resource management
As long as you use the Small Team mode, i.e. sync the Program Board with JIRA Scrum boards, you might take advantage of a nifty resource-related feature. Namely, dragging and dropping a task to a team’s row will mark it with a special label in JIRA.
Protip: Hold Ctrl/Cmd to multi-select tasks on the Board in BigPicture.
You can customize which field the labels are stored in using the global configuration:
Many clients create a custom field of “label” type, name it Team and add it to the Gantt module’s left pane. This way, the Gantt module will show tasks assigned to whole Teams on the Program Board.
Having the ability to assign a task to a team, but no specific assignee just yet, has a few benefits. It assists in your planning, especially during the initial drafts. It also lets you play with what-if scenarios, as changing the team will not affect anything in JIRA, other than its label of course.
Export
All resource-related data is included in your exports. This is especially useful when it comes to Microsoft Project, which can show resource over allocation right after opening the file.
Or, you could export that Gantt chart to a pdf file:
A sample Gantt chart exported to PDF
That’s the basic gist of resource management in the BigPicture plugin for JIRA. In the next months developers behind this add-on will add a lot of functionality to resource management, so stay tuned!